West End Circle Railroad Bridge

Location: Pittsburgh PA
Owner: PennDOT
General Contractor/Client: Brayman Construction Corp.
Value: $135,000
Date Complete: March 2003

Project Details:

Erect new single span steel girder bridge over new extended West End Bridge. Railroad bridge consists of 12 girders, weighing 30 tons each. Project also included the installation of miscellaneous steel for structural support.

 


     

Back to Steel Erection Projects

 

 

 